Chloride profiles measured on drilled cores from the 15 concrete blocks placed at the Fehmarnbelt exposure site are presented below. The profiles were measured after approximately six months (203 days) of exposure to the marine environment, and for each block, two cores were drilled, i.e. one from below sea level and one from the splash zone.

All profiles were obtained according to the method described in DS 423.28:1984  Testing of concrete – Hardened concrete – Chloride content, and the data presented below have not been corrected for variations in aggregate packing near the concrete surface.

rn concrete A_chloride profiles_6 months

Femern concrete B_chloride profiles_6 months

Femern concrete C_chloride profiles_6 months

Femern concrete D_chloride profiles_6 months

Femern concrete E_chloride profiles_6 months

Femern concrete F_chloride profiles_6 months

Femern concrete G_chloride profiles_6 months

Femern concrete H_chloride profiles_6 months

Femern concrete I_chloride profiles_6 months

Femern concrete J_chloride profiles_6 months

Femern concrete K_chloride profiles_6 months

 

Femern concrete L_chloride profiles_6 months

Femern concrete M_chloride profiles_6 months

Femern concrete N_chloride profiles_6 months

Femern concrete O_chloride profiles_6 months